Roosevelt Avenue - 6th Street to 12th Street Reconstruction

Project Type:
Street
Project Status: 
Approved and Under Construction
Location: 
Roosevelt Avenue
6th Street - 12th Street
Two Rivers, WI 54241

May 2, 2024 Update
- Contractor continues installation of water main and is currently working south of 10th Street progressing to south of 9th Street.  Water main installation is expected to be completed to this point sometime during the week of 5/7/2024.  Contractor then expects to jump back to sanitary sewer installation.

-Contractor plans to install storm sewer in the Roosevelt and 12th Street intersection starting Monday, May 6.  Upon completion of the intersection work, Public Works staff will place concrete pavement in this intersection to facilitate vehicular traffic.

April 22, 2024 Update
 - Continue installation of water main - working from 12th Street to the south

April 15, 2024 Update
- Completed placement of approximately 900 feet of sanitary sewer (south of 12th Street)
- Performed water main tie-in at 12th & Roosevelt intersection

 

 

 

Roosevelt Avenue reconstruction